Replace MV with D3 Disa
Management Representatives will travel to the Disa Facility to observe the FAT (factory acceptance tests) – 11-10-24 thru 11-13.
FAT – 11-11-24
Ship from Denmark – 11-20-24.
Arrive in New York harbor – 12-13-24.
Onsite at AF – 12-18-24
Shutdown of the Disa MV and Disa 230 (scheduled holiday shutdown) – end of 2nd shift 12-20-24
Installation begins – 12-21-24.
Start up of Disa 230 – 1-02-25.
Start up of the new D3 - Monday 1-13-25.
The AF will be at 50% production for 7 production days after returning from the scheduled holiday shutdown.
The installation of a new 400 amp service has begun.
Melt Minder 300 Upgrade – Scheduled for December 2024 Install.
Didion #2 Replacement – Scheduled for Thanksgiving 2024 Install.